Northeast Harbor Main Street Improvements Project - Spring 2020
Schedule: Northeast Harbor Main Street Improvements Project Spring, 2020
Location of work: the Work Area for April and May this year is generally both the North and South ends of the project as well as Summit Road.
Traffic Control: During construction, one way traffic in the southerly direction will be maintained. There may be occasions when there are temporary waits to pass due to a task being worked on. We will strive to keep this to a minimum.
Main St. Access: During construction, we ask that drivers try to avoid driving through the construction zone if possible. Most locations on Main Street can be accessed by more than one route.
Schedule: Subject to change due to weather or unforeseen conditions.
Week of April 6:
• Install Electric vault in front of 127 Main St.
• Install yard hydrant in island on at intersection of Main and Kimball
• Install conduit on west side of street, starting around 151 Main headed North
• Excavate sidewalk and install aggregate base.
Week of April 13:
• Continue conduit on West side of Main Street headed North
• Install granite curb beginning at Kimball headed North
Week of April 20:
• Continue conduit on West side of Main Street headed North
• Continue installing granite curb on West side of Main Street headed North
• Begin installing concrete sidewalk at Kimball headed North
• Install drain manhole, catch basin and storm drain on North end of Main Street
Week of April 27:
• Continue conduit on West side of Main Street headed North
• Continue installing granite curb on West side of Main Street headed North
• Begin installing concrete sidewalk at Kimball headed North
Week of May 4:
• Continue conduit on West side of Main Street headed North
• Continue installing granite curb on West side of Main Street headed North
• Continue installing concrete sidewalk on West side of Main Street headed North
Week of May May 11:
• Continue conduit on West side of Main Street headed North
• Continue installing granite curb on West side of Main Street headed North
• Continue installing concrete sidewalk on West side of Main Street headed North
Week of May May 18:
• Cleanup and prepare for pavement
• Pave trenches
• Demobilize for Summer