Updated Schedule: Northeast Harbor Main Street Improvements Project - Update

December 2019 through Janaury 2020
Northeast Harbor

 

Northeast Harbor Main Street Improvements Project

December, 2019 through January, 2020


Location of work: the Work Area for December and January this season is primarily on the Southern end of the project and from Sea Street south.


Traffic Control: During construction, one way traffic in the southerly direction will be maintained.  There may be occasions when there are temporary waits to pass due to a task being worked on.  We will strive to keep this to a minimum.


Main St. Access:  During construction, we ask that drivers try to avoid driving through the construction zone if possible. Most locations on Main Street can be accessed by more than one route.


Schedule: Subject to change due to weather or unforeseen conditions.


Week of December 9:
•     Install water main on Main Street
•     Install storm drain on South end
•     Install 6” HDPE water line on Neighborhood Road

Week of December 16:
•     Test and Disinfect water main on Main Street
•     Install 4” fire protection services
•     Continue storm drain between Sea Street and Kimball Lane

Week of December 23:
•     Install domestic water services on Main Street
•     Continue storm drain between Sea Street and Kimball Lane
•     Test and disinfect 6” HDPE water on Neighborhood Road
•     No work on December 25th in observance of Christmas

Week of December 30:
•     Install water services on Neighborhood
•     Install storm drain on Neighborhood
•     Install 8” storm drain on Main Street
•     No work on January 1st in observance of New Year’s Day

Week of January 6:
•     Install 8” storm drain on Main Street
•     Remove ledge on West side of Main Street in preparation for installation of electrical vaults

Week of January 13:
•     Remove ledge in preparation for installation of electrical vaults
•     Install electrical vaults on West side of Main Street

Week of January 20:
•     Install electrical vaults on West Side of Main Street
•     Begin electrical trenching under sidewalk under West side of Main Street starting at the South end and headed North


Week of January 27:
•     Install electrical trenching under sidewalk under West side of Main Street headed North from the South end

OCTOBER and NOVEMBER

Location of work: the Work Area for October and November this year is generally both the North and South ends of the project as well as Summit Road.

Traffic Control: During construction, one way traffic in the southerly direction will be maintained.  There may be occasions when there are temporary waits to pass due to a task being worked on. We will strive to keep this to a minimum.

Main St. Access:  During construction, we ask that drivers try to avoid driving through the construction zone if possible. Most locations on Main Street can be accessed by more than one route. 

Schedule: Subject to change due to weather or unforeseen conditions.

Week of October 21:
•     Disinfect 12” water main on Summit
•     Install water services on Summit
•     Install Valve on Main Street
•     Begin 12” water main at South End headed North
•     Begin storm drain at Sea Street headed North

Week of October 28:
•     Continue 12” water main on South End headed North
•     Continue storm drain between Sea Street and Summit
•     Disinfect 12” water main on Main Street Week of November 4:
•     Install water services on Main Street
•     Install storm drain on Main Street, North of Summit
•     Install 6” HDPE water on Kimball Road

Week of November 11:
•     Install water services on Main Street
•     Install storm drain on Main Street, North of Summit
•     Install storm drain cross-pipes and basin inlets starting at Sea Street headed North

Week of November 18:
•     Install storm drain cross-pipes and basin inlets starting at Sea Street headed North
•     Test and disinfect 6” HDPE water on Kimball
•     Start Sewer North of Sea Street, headed North Week of November 25:
•     Install Storm Drain on South end
•     Continue Sewer to Summit
•     Thanksgiving – No work Thursday or Friday